Millbrook Footbridge Refurbishment

DJI 0006 (1)

Summary

  • Where: Millbrook Road Footbridge
  • When: Summer 2023
  • What: Refurbishment works to Millbrook Road Footbridge between Foundry Lane and Millbrook Railway Station
  • Why: To make the footbridge more attractive and provide a long-term refurbishment to the existing footbridge structure
  • How: Works will be funded by capital monies allocated by the Council and grant funding

Latest News

The Council’s Highways Partnership have commissioned refurbishment works to begin in July 2023. This builds upon the works that Network Rail undertook to Millbrook Footbridge in April 2021 providing a direct connection between Foundry Lane and the Millbrook Railway Station platform.

A preferred contractor has been selected for delivery of the scheme providing a long-term refurbishment of the existing footbridge. These works will largely include extensive coating removal and repainting of the entire structure (carried out whilst the bridge is surrounded with scaffolding). There will also be new surfacing provided across the footbridge and improvements made to the existing ramp access and overgrown vegetation in Foundry Lane.

Project Details

Works to Millbrook Footbridge will begin on Monday 10th July and are anticipated to last for approximately 7 weeks. This ensures the scheduled completion of the works will allow the footbridge to be reopened before the end of the school Summer holidays.

Throughout the works, scaffolding will be erected surrounding the bridge and it will be enclosed with protective sheeting to ensure that the works can be carried out safely above Millbrook Road West. As a result, it will therefore not be possible to maintain pedestrian routes across the bridge whilst the works are carried out. The following diversion routes will therefore be in place from Monday 10th July:

Map showing pedestrian diversion routes via Regents Park Road junction and Paynes Road.

Whilst the works are carried out, traffic will be maintained on Millbrook Road West wherever possible, as it is recognised that this is key route into the City, although some overnight road closures and lane restrictions will be required. The planned programme for these closures and restrictions is detailed below:

Date(s)

Work to be undertaken

Road closure/restriction details

11th – 12th July

(2 nights)

Structural work (South side)

Closure of the slip lane from Paynes Road onto Millbrook Road West westbound (heading out of the City).

Access from Paynes Road into Waterloo Road will be maintained with the closure in place after this junction.

13th July

(1 night)

Structural work (North side)

Two-lane restriction in place on Millbrook Road West eastbound (heading towards the City Centre).

Access to Regents Park Road and Paynes Road will be maintained.

17th – 20th July

(4 nights)

Bridge preparation works

Full closure of Millbrook Road West in both directions between Regents Park Road* and Central Station Bridge.

*Right-turn from Millbrook Road West onto Millbrook Point Road (at the Regents Park Road junction) will also be unavailable, with vehicles diverted via Third Avenue.

24th – 28th July

31st July

(5 nights)

Scaffolding installation

Full closure of Millbrook Road West in both directions between Regents Park Road* and Central Station Bridge.

*Right-turn from Millbrook Road West onto Millbrook Point Road (at the Regents Park Road junction) will also be unavailable, with vehicles diverted via Third Avenue.

14th – 18th August

(5 nights)

Scaffolding removal

Full closure of Millbrook Road West in both directions between Regents Park Road* and Central Station bridge.

*Right-turn from Millbrook Road West onto Millbrook Point Road (at the Regents Park Road junction) will also be unavailable, with vehicles diverted via Third Avenue.