Summary

  • Where:¬†Bassett Avenue
  • When:¬†From Monday 21 October for 1 week
  • What:¬†Junction crossing improvements¬†
  • Why: Improve safety for walking and cycling

Project Details

A coloured surface treatment will be laid on each junction, in order to provide a visual crossing to enhance safety for pedestrians and cyclists. The work is expected to take 1 week.

In order to carry out the work safely, the work will be carried out overnight and the junctions will be closed one at a time whilst the treatment is being laid. The working hours will be between 8pm and 6am.

We expect each junction to be closed for approximately 2-3 hours, and due to the speed of the treatment process, approximately 2-3 junctions can be completed in one night. We will be starting at the junction with The Spinney and working southbound to the junction with Beechmount Road.