Scheme Overview
This map shows the areas of work that will be completed in this scheme; they are numbered in chronological order. Please refer to the drop downs below to see the details of each area.
1. Southampton Cycle Network - COMPLETE
There are several areas where we will be widening the northside footway to create a segregated footway/cycleway:
1a. Between the opposite of the end of Butt's Road and Warburton Road
From 25 February for 7 weeks
1b. Between White's Road and Bath Road & between Bath Road and Upper Deacon Road
From late Summer for 3 weeks
1c. Between Hinkler Road and Gavan Street
From early Autumn for 4 weeks
1d. Between Upper Deacon Road and North East Road
From mid Autumn for 6 weeks
1e. Between North East Road and Hinkler Road
From mid Autumn for 4 weeks
1f. Between Gavan Street and opposite Butt's Road
From mid Autumn for 4 weeks
2. Coates Road and Warburton Road - COMPLETE
The work will include:
- New junction signals
- Widening of existing crossings
- A new Toucan crossing at Coates Road
- A new contraflow cycle lane on Coates Road and narrowing Coates Road to one lane
- New right turn into petrol station
3. Orpen Road - COMPLETE
*Complete*
The work will include:
- New junction signals
- Widening of existing crossings
- Removal of gating system (will allow exit from Orpen Road onto Bursledon Road at all times)
- Removal of on-road cycle lane
- Extension of left turning lane
- Footway widening
4. Highpoint Centre - COMPLETE
*Complete*
The work will include the creation of a continuous segregated footway/cycleway across the entrance, which will give right of way to pedestrians and cyclists over turning traffic.
5. Kathleen Road - COMPLETE
Being kept closed while Hinkler Road is running on temporary signals.
The work will include:
- New junction signals
- 2 new Toucan crossings
- Footway widening to create a shared use footway/cycleway
- Removal of bus lane to create straight ahead/left hand turn lane into Kathleen Road
6. Chatsworth Road - COMPLETE
From late June for 2 weeks
The work will include the removal of the right turn into Chatsworth Road, as it contravenes DfT safety guidelines by crossing a dual carriageway without control of traffic signals.
7. White's Road - COMPLETE
From mid Summer for 4 weeks
The work will include:
- New junction signals
- 2 new Toucan crossings
8. Deacon Road and Upper Deacon Road - COMPLETE
From mid Summer for 12 weeks
The work will include:
- New junction signals
- New Toucan crossing
- Removal of on-road cycle lane
- Relocation of bus stop
- Conversion of verge into a segregated footway/cycleway
9. Hinkler Road - COMPLETE
From mid Summer for 6 weeks. Road currently open under temporary signals while the main signals are replaced. This requires Kathleen Road to be closed until the main signals are back on from 20 September for six weeks.
The work will include:
- New junction signals
- 3 new Toucan crossings
- New footway for pedestrians parallel to Carey Road (removal of existing footway)
- New raised surface cycleway on Carey Road
- Creation of additional eastbound lane to turn right into Kathleen Road
10. Gavan Street - COMPLETE
From mid Summer for 16 weeks
The work will include:
- New junction signals
- New Toucan crossing
- Priority footway/cycleway across car park access
- New dedicated left turn into retail park
- Moving the 40mph limit 90m east
11. Bursledon Road and Maybray King Way - COMPLETE
From late Summer for 12 weeks
The work will include:
- New junction crossing
- New dedicated right turn lane into White’s Road
12. Botley Road - COMPLETE
From mid Autumn for 12 weeks
The work will include:
- New junction signals
- New Toucan crossings
- New separate cycle crossing
13. Ruby Road and Bath Road - COMPLETE
From late Autumn for 9 weeks
The work will include:
- New junction signals
- 3 new Toucan crossings
- Junction widening of A3024 inbound
- Removal of no right turn out of Bath Road
14. North East Road - COMPLETE
From late Autumn for 6 weeks
This work will include:
- New junction signals
- 3 new Toucan crossings
- Remove bus lay by and shelter, and install new bus stop