Work on West Quay Road has now been completed. The photos below show some of the finished works. We appreciate your cooperation from individuals impacted by the road construction.
Phasing of work
Balfour Beatty is working in partnership with Southampton City Council to manage the highways service across Southampton. As part of this, we are improving access for pedestrians and cyclists along West Quay Road from Herbert Walker Avenue to Harbour Parade (see map).
Phase 1: 19 October for up to 1 week - Herbert Walker Avenue junction with Mayflower Roundabout
These works are now finished.
Phase 2: 19 October for up to 2 weeks overnight – West Quay Road service road to the industrial area (see map)
These works are now finished.
Phase 3: 26 October for up to 3 weeks – West Quay Road from Mayflower Roundabout to Harbour Parade
These works are now complete.
Phase 4: 2 November for up to 3 weeks – Exit to West Quay Service Road
These works are now finished.
Phase 5: Week commencing 23 November for up to 1 week – West Quay Road southbound, between Harbour Parade to Ikea
The works are now finished.