Summary
- Where: Redbridge Flyover, Redbridge Road Slip Road & Green Park Road
- When: 24 November - 3 December 2021
- What: Resurfacing works on Redbridge Flyover, Redbridge Road Slip Road and Green Park Road.
- Why: Improve conditions the carriageways
The work is programmed as follows:
Redbridge Flyover (Outbound)
Re-surfacing - 24 & 25 November 2021
Working hours will be overnight 8pm– 5am.
To ensure the safety of the operatives the flyover will be closed, outbound only, with a signed diversion in place.
Iron works – 29 & 30 November 2021
Working hours will be overnight 8pm– 5am.
To ensure the safety of the operatives there will be lane closures in place on the flyover, outbound only.
Redbridge Road Slip Road (In-bound)
Re-surfacing - 25 & 26 November 2021
Working hours will be overnight 8pm– 5am.
To ensure the safety of the operatives the Redbridge Road will be closed from just before property number 76 to the roundabout, with a signed diversion in place.
Iron works – 26 November 2021 & 29 November - 3 December 2021.
Working hours will be overnight 8pm– 5am.
To ensure the safety of the operatives there will be lane closures in place.
Green Park Road
Re-surfacing - 26 & 29 - 30 November 2021
Working hours will be 7:30am – 5:30pm.
To ensure the safety of the operatives Green Park Road will be closed in two phases, with signed diversions in place.