- Where: Above Bar Street and it's junction with New Road and Civic Centre Road
- When: 1 June 2026
- What: Replace and upgrade traffic signals, footway improvements and maintenance, drainage improvements and carriageway resurfacing
- Why: To replace aging infrastructure and make general improvements for pedestrians, cyclists, taxis and buses
- How: Funded by through the Bus Service Improvement Plan
Project Details
Funded by through the Bus Service Improvement Plan, the works will include:
- Replacing and upgrading the traffic signals at the junction of Above Bar Street, Civic Centre Road and New Road for all users with:
- Improved pedestrian detection and vehicle detection for more efficient running of the junction as well as more flexibility in meeting the demands of the network
- Bus priority detection to improve bus service journey times
- Countdown timers for pedestrians’ crossings
- Early release lights for cyclists
- Making the bus stop infill on Above Bar Street permanent by replacing existing materials with those matching the surrounding for example replacing tarmac surfacing with paving and replacing rubber kerbs with Kassell kerbs in keeping with rest of the kerb line. The infill is also reduced in width to better allow the passing of buses
- Resurfacing of the carriageway
- Resolving defects on footways including broken or rocking paving
- Improving the drainage of footways
- Cleaning of lighting columns and cutting back of tree canopy along Above Bar Steet where required
- Changes at city centre junctions to permit taxis to make the same movements as buses including at Above Bar Street / New Road and Park Road / Havelock Road improving accessibility for them
The works are scheduled to take place from Monday 1 June 2026 and are expected to take 8 weeks. During this time, to ensure the safety of the public and Balfour Beatty's workforce, Above Bar Street will be closed from the junction with New Road and Civic Centre Road to the junction with Pound Tree Road on the south side, and from the junction to Commercial Road on the north side. At times it will also be necessary to close the junction of Above Bar Street, New Road and Civic Centre Road overnight.
We appreciate that Above Bar Street is a key travel corridor and apologise for the inconvenience caused. The taxi rank adjacent to Palmerston Park will be temporarily relocated to Civic Centre Road nearby to La Tavernetta and the bus stops here will also be temporarily suspended. Details for all the effected services can be found on the Bluestar website.
|
|
Above Bar / New Road / Civic Centre Road Junction | Above Bar South |
| Weeks 1-5 |
Works will begin on the northern corners of the junction (near KFC and Sprinkles). The works will then move to the southern corners (near the park entrance). Mainly daytime working, with occasional night-time works where required. |
Bus stop improvement works New drainage installation Paving works to the temporary bus stop build-outs Daytime working |
| Weeks 5-6 |
Traffic signal commissioning and set-up Daytime working |
Associated repair works in the area Daytime working |
| Weeks 7-8 |
Resurfacing and road marking works Night-time working |
Resurfacing and road marking works Night-time working |